Hi everybody,

we are facing a scenario where our customer needs to schedule 20 days of a resource. Which is the best approach? Create a requirement with 8 hours per day that will create 20 bookings or 1 booking including non working hours?

I'm doing this question because with first solution we found a large use of POA with automatic FS shares to user Resource and async service is very stressed for a couple of minutes...

Anyone can suggest us something?

Thank you very much.