Hi,
We have accidentally entered standard cost where the effective date is set at future date.
Hence there is no effective standard cost at effective date.
I have tried to enter updated standard cost where effective date is set at current date.
However, the AX does not accept new proposed effective date that is before the existing effective date.
How could I either:
1. Delete existing standard cost
2.Override effective date of existing standard cost
3.Let new up to date standard cost be recognised
Sincerely,
ABTS